interior design, renovation work, tiling work, plumber work
All the tiling works for living, kitchen and 02 bathroom had finish and as you can see its still very dirty and messy. i’m still pressing for time to finish on 25 Feb. During the removal of existing false ceiling and cornice from the previous owner, cost a lots of debris and holes on the ceiling and the wall during the removal. At the mean time, the plumber workers were arranged to come in to lay the stainless steel piping for kitchen and both bathroom not forgetting the bathroom ware . i also manage to arrange for the city gas contractor to lay the gas piping to the stove area on the same day. The reason is that i need not be at the job site to wait for the gas contractor. It’s just wasting time……….:)
What is next?